Thursday, June 1, 2017

Affordable Container Housing

Assessed home time & cost to build - 1,000 Homes @ 680 sq. ft.

Container Homes - Off site build, prep, transport, install

12 Weeks site work, underground, foundations and common areas, begins simultaneously with prefabrication.
8 Weeks to prefabricate roughed out units
4 Weeks to ship
4 Weeks installation and finish

Container cost - $1,000-$2,000 each, depending on size, condition

Prefabrication - $6,000-$8,500

Shipping - $4500-$6000, based on weight, Five people required per residence
built in 100 unit blocks.

Underground & foundations - $2,000-$3,500

Installation, common areas, finishes - $3,000-$5,000

Housing units - 2 containers

$16,500-$25,000 Per units for a finished ready to live in container home

1,000 Families or approximately 5,000 people - $16,500,000 - $25,000,000

Cost per sq. ft. - $24.26 - $36.76 vs. Standard Construction $75 - $150